Urban Renewal Business Implementation Status

 
(1)   Renewal promotion status  
As of July 31, 2009, 84 cases have already been approved, area: 27.69 hectares(18 cases have been completed, 30 cases still in construction)。
Implement act
Approved: 26 cases, area: 7.6 hectares, completed
Urban Renewal Act received 432 application cases
Approve urban renewal business outline
331cases
Assist in organizing renewal group
25cases
Apply for urban renewal business plan (Rights transformation plan)
183cases
Review and pass by committee
92cases
Approve for implementation
84cases
In construction
30cases
Completed
18cases
 
(2)    Status of implemented urban renewal cases
Implementation stage/timeframe
Business Summary
Business Plan
Applications
Approved by city government
Applications
In public exhibition
Reviewed and passed by the committee
Approved for implementation
Until the end of 2006
191
159
88
54
38
31
2007
89
73
24
30
21
19
2008
77
79
41
30
23
20
2009
35
20
30
17
10
14
Total
392
331
183
131
92
84
 
(3)   Review Status of Cases Presented to the Urban Renewal Review Committee for 2008
 
Type of meeting
Executive meeting
Committee meeting
Project team meeting
Project committee meeting
No. of times
47
19
1
0
No. of cases
47
74
1
0
 
(4)    Cumulative approved implemented 84 renewal cases and results
 From 1998, when the Autonomous Urban Renewal Act was announced up until July 31, 2009, 84 cases have been approved for implementation with acreage of 27.69 hectares (18 cases have already completed and 30 cases are still in construction). These cases have jointly created a real estate value of NT$232. 207 billion, which is first nationwide, both in terms of quality and quantity. The public benefits of the approved renewal cases including the settlement of 5,044 households (4,078 households from legal structures and 966 households from illegal structures), assist in the opening roads (18,483㎡, equivalent to a road length of 2,447meters), increase number of parking spaces for 15,595 cars and 26,566 motorcycles, reserved 47,294㎡ (length of road: 9,099meters) for pedestrian footpaths and 3,680.85㎡public facilities provided to the community.
 Item
Results
1.      Settlement of current residents
Legal buildings4,078households; illegally built structures 966 households
2. No. of households after renewal
11,585households
3. Adding parking spaces
Cars 15,595units, motorcycles 26,566 units
4. Reserved for charitable facilities
3,680.85㎡ (three Wenkang facility sites, one leisure facility site, one community activity center
5. Assist in opening planned roads (including land and construction expenditures)
18,483㎡, length of road: 2,447 meters, savedthe city government NT$927 million
6. Reserved for pedestrian footpaths
47,294㎡, length of road: 9, 099 meters
7.Urban renewal implementation expenditure
NT$115.82 billion
8. Creating real estate value
NT$232.20 billion